Economy · Explainer
3 Best Saudi Price Indices for a Construction Budget
Choosing a wholesale index over a residential construction index added SAR19,000 to the same hypothetical estimate.

Kunkafa News · Published · 2 min read
By Kareem FaridDiscuss with the author on X
Key points
- The residential index raised the illustrative estimate by SAR10,000.
- Weights in a specific project can change the size of the adjustment.
A Saudi contractor who updated a SAR1 million residential construction estimate using wholesale inflation would have added SAR29,000 in October 2025. Using the national residential construction index would have added SAR10,000. The SAR19,000 gap comes entirely from the choice of benchmark. [1][2]
The comparison holds the job, quantities and starting estimate constant. Each annual change updates the same hypothetical October 2024 budget to October 2025 prices. The ranking reflects how closely each basket matches costs a residential contractor pays.
1. Construction Cost Index for the whole job
The residential measure rose 1.0%. It covers four cost groups, including labour and equipment rental, which a materials invoice misses. A SAR1 million estimate becomes SAR1.010 million. The corresponding non-residential reading was 0.9%, so the choice of building type also matters. [1]
2. Wholesale Price Index for purchasing materials
Wholesale prices rose 2.9%. That puts the same estimate at SAR1.029 million. The detailed commodity groups make this series useful when questioning a supplier about price movements, although a national wholesale basket includes goods a particular builder never buys. [2]
The Capsule
- Start a whole-project estimate with the residential construction series.
- Use the relevant wholesale commodity group for a materials quote.
- Recalculate with the quantities and cost weights in the tender.
3. Consumer Price Index for household context
Consumer prices rose 2.2%, producing a SAR1.022 million estimate. The index measures what households spend on a basket of goods and services. It helps explain a client's purchasing power, while its weights say little about the crew, crane and materials required on site. [3]
When the bill of quantities changes the answer
In residential construction, GASTAT recorded basic materials up 0.1%, labour up 1.5%, equipment rental up 1.2% and energy up 9.9%. A fast-rising input can have a modest effect on a job that uses very little of it. [1]
Suppose a particular estimate splits 60% to materials, 30% to labour, 8% to equipment and 2% to energy. Applying the four changes produces an increase of SAR8,040. Energy contributes SAR1,980, while labour contributes SAR4,500 because it starts from a much larger base.
For an actual tender, match those weights to the cost breakdown and check recent supplier quotes. For a signed agreement, read the escalation clause before applying any index. A comparison of national prices alone establishes neither the payment due nor the contractor's margin.
Sources: [1] GASTAT construction costs, October 2025 · [2] GASTAT wholesale prices, October 2025 · [3] GASTAT consumer prices, October 2025.
Kunkafa forecasts
Brent oil
How far it could move, which way, by when, and how confident Kunkafa is.
Check the latest forecastsMore in Economy

Egypt Opens a Path for 1.2 Million Sole Owners to Take Partners
A business could keep its registration number, contracts and history as it becomes a company. A separate registry would record financing convertible into equity.

Saudi PIF Seeks a Buyer for Up to a Quarter of Newcastle United
New shares would put money into the club as it plans a £190 million training ground and weighs a bigger stadium.

Egypt and Chevron Work Out a 280km Route for Cyprus Gas to Port Said
Cairo shares edged higher on Thursday as Egypt explored French funding for startups. In Giza, families mourned the victims of the Ring Road fire.