Economy · Explainer

Abu Dhabi Gets Nearly Half Its Power From Clean Sources

Nuclear, solar and wind rose from under 5% of generation in 2020 to nearly 46% in 2025. A $6.1 billion solar-and-battery plant faces its next test after sunset.

An Emirati grid engineer watches the sun set over solar panels, batteries and the domes of a nuclear power station.
An Emirati grid engineer watches the sun set over solar panels, batteries and the domes of a nuclear power station.Kunkafa AI market forecasts and analysis tool

Kunkafa News · Published · 5 min read

Kareem FaridBy Discuss with the author on X

Here is a visual story in summary

1 / 6
Abu Dhabi Gets Nearly Half Its Power From Clean Sources Nuclear, solar and wind supplied almost 46% of the electricity generated in 2025. Five years earlier, they supplied less than 5%. · Kunkafa · Nov 23, 2026
Abu Dhabi Gets Nearly Half Its Power From Clean Sources Nuclear, solar and wind supplied almost 46% of the electricity generated in 2025. Five years earlier, they supplied less than 5%. · Kunkafa · Nov 23, 2026Kunkafa AI market forecasts and analysis tool
Barakah works the night shift Four reactors joined the grid between 2020 and 2024. They can keep supplying electricity long after sunset. · Kunkafa · Nov 23, 2026
Barakah works the night shift Four reactors joined the grid between 2020 and 2024. They can keep supplying electricity long after sunset. · Kunkafa · Nov 23, 2026Kunkafa AI market forecasts and analysis tool
Daylight adds another source Noor Abu Dhabi and Al Dhafra supply solar power. With nuclear and wind, clean generation rose roughly twelvefold in five years. · Kunkafa · Nov 23, 2026
Daylight adds another source Noor Abu Dhabi and Al Dhafra supply solar power. With nuclear and wind, clean generation rose roughly twelvefold in five years. · Kunkafa · Nov 23, 2026Kunkafa AI market forecasts and analysis tool
A factory still needs power at midnight The annual average hides an hourly problem. The motors on a night shift need electricity just as the solar panels stop producing. · Kunkafa · Nov 23, 2026
A factory still needs power at midnight The annual average hides an hourly problem. The motors on a night shift need electricity just as the solar panels stop producing. · Kunkafa · Nov 23, 2026Kunkafa AI market forecasts and analysis tool
Save the sunlight for later Masdar and EWEC are building a solar plant with batteries. It is designed to deliver one gigawatt around the clock from 2027. · Kunkafa · Nov 23, 2026
Save the sunlight for later Masdar and EWEC are building a solar plant with batteries. It is designed to deliver one gigawatt around the clock from 2027. · Kunkafa · Nov 23, 2026Kunkafa AI market forecasts and analysis tool
Why finance a new gas plant too? Taweelah C secured financing on November 23. Its planned 2.6 gigawatts would help meet demand when solar output dips. · Kunkafa · Nov 23, 2026
Why finance a new gas plant too? Taweelah C secured financing on November 23. Its planned 2.6 gigawatts would help meet demand when solar output dips. · Kunkafa · Nov 23, 2026Kunkafa AI market forecasts and analysis tool

In 2020, less than five of every 100 units of electricity generated in Abu Dhabi came from nuclear, solar and wind together. By 2025, those sources supplied almost 46 out of every 100, according to operating data the Emirates Water and Electricity Company (EWEC) released on November 5. On November 23, the emirate also secured financing for a new gas-fired power plant. The gas plant and a separate giant battery project tackle a problem the annual figures conceal. Who supplies a factory’s night shift after the solar panels stop producing? [1] [2]

Key points

  • Annual output from nuclear, solar and wind reached more than 49.3 terawatt-hours in 2025.
  • Masdar aims to supply one gigawatt around the clock from a solar farm and batteries starting in 2027.
  • The newly financed Taweelah C gas plant would add 2.6 gigawatts of flexible capacity.

Where the extra electricity came from

EWEC counted more than 49,300 gigawatt-hours of clean electricity in 2025, roughly 12 times the 4,100 gigawatt-hours generated in 2020. The four Barakah reactors began supplying the grid in stages between 2020 and 2024, providing power around the clock. Noor Abu Dhabi and Al Dhafra contributed solar electricity during daylight. The figures measure electricity actually generated over a year. [1]

Measure20202025
Electricity from nuclear, solar and windAbout 4.1 TWhOver 49.3 TWh
Share of all electricity generated in Abu DhabiUnder 5%Almost 46%

EWEC operating data, November 5, 2026. One terawatt-hour is 1,000 gigawatt-hours.

What powers the night shift?

Consider a factory running a night shift. Its motors still need a steady supply after the solar panels stop producing. Masdar and EWEC are building a plant with 5.2 gigawatts of solar panels and batteries that can store 19 gigawatt-hours. The design calls for the system to deliver one gigawatt continuously, using stored daytime electricity after dark. Masdar secured financing in July for the $6.1 billion project and expects operations in 2027. Its first year of operation should show how the design performs on the grid. [3]

Abu Dhabi is also buying flexibility from gas. TAQA, EWEC, Aljomaih and Sembcorp said on November 23 that financing was in place for the AED 7.76 billion Taweelah C plant, where early works are under way. Its 2.6 gigawatts of planned gas-fired capacity give the operator another way to match demand as solar output varies. TAQA holds 60% of the project company. Gas releases carbon when burned and sits outside EWEC’s clean-generation figures. [2]

We announced today that renewable and clean energy generation across Abu Dhabi, powered by nuclear, solar, and wind, has increased by over 1,000 per cent between 2020 and 2025, reflecting the success of the Emirate's energy transition. This progress reflects our long-term… Show more

When Masdar broke ground in October 2025, creator Nuseir Yassin welcomed the promise of solar electricity after sunset. A January 2026 discussion turned to its cost and where else the same design might work. These posts predate the July financing.

Perspectives on Abu Dhabi’s power after dark

1 / 4
Creator Nuseir Yassin welcomes the project at its groundbreaking.
Nuseir Yassin (@nasdaily), October 26, 2025, 08:06 UTC. Excerpt: “A gigascale solar plant that works 24/7 is revolutionary.”Kunkafa AI market forecasts and analysis tool
John Hanger explains the solar and battery pairing.
John Hanger (@johnrhanger), January 23, 2026, 14:12 UTC. Excerpt: “UAE broke ground on a 5.2 GWdc PV facility paired with 19 GWh of battery storage in Abu Dhabi in October 2025.”Kunkafa AI market forecasts and analysis tool
Hugh Choi raises the question of the cost of steady solar output.
Hugh Choi (@hyunjun_h_choi), January 23, 2026, 22:21 UTC. Excerpt: “Oversizing generation by 5x to achieve firm output drastically reduces the capital efficiency of solar assets.”Kunkafa AI market forecasts and analysis tool
Niels Harksen asks which climates can replicate the project.
Niels Harksen (@HarksenNiels), January 23, 2026, 23:27 UTC. Excerpt: “a blueprint for similar projects near the equator.”Kunkafa AI market forecasts and analysis tool

Sources: [1] EWEC, November 5, 2026 · [2] Taweelah C partners, November 23, 2026 · [3] Masdar, July 13, 2026